Taichung Combined Cycle Power Plant Project

Project Description

Background

Respond to the growth of domestic power consumption, Taiwan Power Company (TPC) follows the government’s energy policy and promotes the " Taichung Combined Cycle Power Plant Project" to ensure stable power supply. TPC plans to install two gas-fired Combined Cycle units in adjacent to the existing Taichung coal-fired Power Plant station , with a total capacity of about 2.6million kilowatts. This project also includes one berth liquefied natural gas(LNG) unloading pier, a LNG gasification terminal with five LNG storage tanks and associated auxiliary facilities and pipelines, which will be TPC’s first built and self-operated LNG terminal.

Project Location and Scope

The Taichung Combined Cycle Power Plant Project, covering an area of 13.4 hectares, is seated in the Southern of Unit 9 and Unit 10 coal-fired units of Taichung Power Plant.

TCPP Project Plant Overall Location
TCPP Project Plant Overall Location

 

New Design Units Specification

Item Parameters
No. of Unit 2
Single Unit Capacity 1.3 million kilowatts each
Unit Type two gas-fired Combined Cycle units
Thermal Efficiency 64.1% (LHV, Net)
Net Combustion 5,616.22 kJ / kWh (LHV, Net)
Gas turbine indoor type, heavy duty for power generation (Heavy Duty), 3,600 rpm
Steam Turbine longitudinal series, condensing, 3,600 rpm
Heat Recovery Steam Generator  indoor type, triple pressure reheating
Generator hydrogen or air cooled
Transformer outdoor oil immersion

 

Progress Status

Project Progress

Overall progress(%)(March-2026)
Schedule Actual Difference
63.53 63.53 0
 
Commercial Operation Date (COD)/
Obtaining Electricity Generation License
Unit 1 Unit 2
2026/08/31 2027/03/31

Note: The revision of the Taichung Combined Cycle Power Plant Project approved by the Executive Yuan’s letter No. 1141031406 on Jan. 15,2026.

Construction Status:

  1. Power Block: #1 first fire on 2025/6/30. commissioning test are currently being carried out; #2 Cable Installation and the construction structure are currently being carried out.

  2. Circulating Water System: #1 MCW system operated on 2025/5/9 ,#2 MCW system operated on 2026/2/13.

Environmental Protection Planning
  1. Selective Catalytic Reduction System (SCR) is used for environmental protection.

    Pollutant Emission Concentration
    SOx 8 ppm
    NOx 5 ppm
    Particulate 10 mg/Nm3